A deficient control has been identified which could result in great harm to an organization should a low frequency threat event occur. When communicating the associated risk to senior management the risk practitioner should explain:
Correct Answer: A
The risk practitioner should explain to senior management that mitigation plans for threat events should be prepared in the current planning period, as this would demonstrate a proactive and responsible approach to risk management. Mitigation plans are documents that outline the actions and resources needed to reduce the likelihood and/or impact of a specific risk scenario. Mitigation plans should include the following elements: * Risk scenario description and risk ID * Risk owner and other stakeholders * Risk response strategy and objectives * Risk response actions and tasks * Resources, costs, and benefits * Roles and responsibilities * Timeline and milestones * Performance indicators and monitoring mechanisms * Contingency plans and triggers Mitigation plans help to address the gap between the current and desired risk levels and align the risk response with the organizational risk appetite and objectives. Mitigation plans also facilitate the communication, coordination, and collaboration among the risk owners and other stakeholders involved in the risk response process. Mitigation plans should be prepared in the current planning period, as this would allow the organization to act timely and effectively in the event of a low frequency threat event. Preparing mitigation plans in advance would also help to avoid or minimize the potential harm to the organization and its reputation. The other options are not the best ways to communicate the associated risk to senior management. Explaining that this risk scenario is equivalent to more frequent but lower impact risk scenarios may not accurately reflect the true nature and severity of the risk. Explaining that the current level of risk is within tolerance may not convey the urgency and importance of addressing the risk. Explaining that an increase in threat events could cause a loss sooner than anticipated may not provide a clear and actionable solution for the risk. References = Four steps for managing risk at the CEO level, IT Risk Resources | ISACA, How to Communicate Risk to Stakeholders | Anitian