You are the project manager of HGT project. You have identified project risks and applied appropriate response for its mitigation. You noticed a risk generated as a result of applying response. What this resulting risk is known as?
Correct Answer: B
Section: Volume B Explanation: Secondary risk is a risk that is generated as the result of risk response. Incorrect Answers: A: A pure risk is a risk that has only a negative effect on the project. Pure risks are activities that are dangerous to complete and manage such as construction, electrical work, or manufacturing. C, D: These terms are not applied for the risk that is generated as a result of risk response.