Valid CRISC Dumps shared by ExamDiscuss.com for Helping Passing CRISC Exam! ExamDiscuss.com now offer the newest CRISC exam dumps, the ExamDiscuss.com CRISC exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CRISC dumps with Test Engine here:
Mary is the project manager for the BLB project. She has instructed the project team to assemble, to review the risks. She has included the schedule management plan as an input for the quantitative risk analysis process. Why is the schedule management plan needed for quantitative risk analysis?
Correct Answer: B
is incorrect. This is not a valid answer for this questionthroughout theproject, but it is not scheduled during the quantitative risk analysis process. Answer: A is incorrect. When risks are likely to happen is important, but it is not the best answer for thisquestionoption D is incorrect. Risks may affect the project schedule, but this is not the best answer for thequestion.