Explanation/Reference:
Explanation:
A salience model defines and charts stakeholders' power, urgency, and legitimacy in the project.
The salience model is a technique for categorizing stakeholders according to their importance. The various difficulties faced by the project managers are as follows:
How to choose the right stakeholders?

How to prioritize competing claims of the stakeholders communication needs?

Stakeholder salience is determined by the evaluation of their power, legitimacy and urgency in the organization.
Power is defined as the ability of the stakeholder to impose their will.

Urgency is the need for immediate action.

Legitimacy shows the stakeholders participation is appropriate or not.

The model allows the project manager to decide the relative salience of a particular stakeholder.
Incorrect Answers:
B: This defines the power/interest grid.
C: This defines an influence/impact grid.
D: This defines a power/influence grid.