You and your project team are identifying the risks that may exist within your project. Some of the risks are small risks that won't affect your project much if they happen. What should you do with these identified risk events?
Correct Answer: C
Section: Volume C Explanation/Reference: Explanation: Low-impact, low-probability risks can be added to the low priority risk watch list. Incorrect Answers: A: These risks are not dismissed; they are still documented on the low priority risk watch list. B: While these risks may be accepted, they should be documented on the low priority risk watch list. This list will be periodically reviewed and the status of the risks may change. D: Not every risk demands a risk response, so this choice is incorrect.