You are the project manager of the PFO project. You are working with your project team members and two subject matter experts to assess the identified risk events in the project. Which of the following approaches is the best to assess the risk events in the project?
Correct Answer: A
Explanation/Reference: Explanation: Risk probability and assessment is completed through interviews and meetings with the participants that are most familiar with the risk events, the project work, or have other information that can help determine the affect of the risk. Incorrect Answers: B: The true cost of the risk event is not a qualitative risk assessment approach. It is often done during the quantitative risk analysis process. C: The probability and impact matrix is a tool and technique to prioritize the risk events, but it's not the best answer for assessing risk events within the project. D: Root cause analysis is a risk identification technique, not a qualitative assessment tool.