Valid CRISC Dumps shared by ExamDiscuss.com for Helping Passing CRISC Exam! ExamDiscuss.com now offer the newest CRISC exam dumps, the ExamDiscuss.com CRISC exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CRISC dumps with Test Engine here:
Stephen is the project manager of the GBB project. He has worked with two subject matter experts and his project team to complete the risk assessment technique. There are approximately 47 risks that have a low probability and a low impact on the project. Which of the following answers best describes what Stephen should do with these risk events?
Correct Answer: B
Explanation/Reference: Explanation: The low probability and low impact risks should be added to a watchlist for future monitoring. Incorrect Answers: A: The risk response for these events may be to accept them, but the best answer is to first add them to a watchlist. C: Risks are not dismissed; they are at least added to a watchlist for monitoring. D: While the risks may eventually be added to the register, the best answer is to first add them to the watchlist for monitoring.