There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and controlling?
Correct Answer: D
Explanation/Reference: Explanation: Change requests are not one of the four inputs to the Risk Monitoring and Controlling Process. The four inputs are the risk register, the project management plan, work performance information, and performance reports. Incorrect Answers: A, B, C: These are the valid inputs to the Risk Monitoring and Controlling Process.