When it appears that a project risk is going to happen, what is this term called?
Correct Answer: C
Explanation/Reference: Explanation: A trigger is a warning sign or a condition that a risk event is likely to occur within the project. Incorrect Answers: A: Issues are events that come about as a result of risk events. Risks become issues only after they have actually occurred. B: A contingency response is a pre-planned response for a risk event, such as a rollback plan. D: A threshold is a limit that the risk passes to actually become an issue in the project.