Valid COBIT-2019 Dumps shared by ExamDiscuss.com for Helping Passing COBIT-2019 Exam! ExamDiscuss.com now offer the newest COBIT-2019 exam dumps, the ExamDiscuss.com COBIT-2019 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com COBIT-2019 dumps with Test Engine here:
Which of the following MUST be done before an enterprise can determine performance measures for a process improvement initiative?
Correct Answer: C
According to the COBIT 2019 Process Assessment Model, one of the prerequisites for determining performance measures for a process improvement initiative is to perform a process risk assessment. A process risk assessment identifies and evaluates the potential threats and opportunities that may affect the achievement of process objectives. A process risk assessment also helps to prioritize improvement actions based on their impact and likelihood.4, p. 11-12 References: 4: COBIT 2019 Process Assessment Model: Using COBIT 2019