Valid IIA-CIA-Part1 Dumps shared by ExamDiscuss.com for Helping Passing IIA-CIA-Part1 Exam! ExamDiscuss.com now offer the newest IIA-CIA-Part1 exam dumps, the ExamDiscuss.com IIA-CIA-Part1 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com IIA-CIA-Part1 dumps with Test Engine here:
When performing an audit of the risk management process an auditor makes the observations listed below. Which poses the greatest risk to the organization?
Correct Answer: C
When assessing the greatest risk among the provided observations in the audit of the risk management process, we must evaluate which issue could most significantly impact the organization's ability to manage risks effectively. Here is a detailed analysis of each option: * Option A: While not reviewing identified risks for completeness in the past two years is a concern, it does not necessarily imply that new risks have not been identified or managed during that time. * Option B: Not testing controls annually to confirm operating effectiveness is a significant issue, but existing controls may still be functioning effectively. * Option C: An informal and poorly documented process to identify and evaluate new risks presents a critical weakness. This means the organization might be unaware of emerging risks, leading to unmanaged exposures that could cause significant harm. * Option D: Not ranking identified risks to establish their importance affects prioritization but does not prevent risk identification or basic management. The greatest risk is posed by Option C because an informal and poorly documented process to identify and evaluate new risks undermines the entire risk management framework, potentially allowing significant and emerging risks to go unrecognized and unaddressed. References: * The Institute of Internal Auditors (IIA) Standards and Guidance on Risk Management. * COSO ERM Framework.