Valid CASPO-001 Dumps shared by ExamDiscuss.com for Helping Passing CASPO-001 Exam! ExamDiscuss.com now offer the newest CASPO-001 exam dumps, the ExamDiscuss.com CASPO-001 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CASPO-001 dumps with Test Engine here:
Who updates work remaining during the Sprint? (Choose the best answer)
Correct Answer: B
The Developers own the Sprint Backlog and update it as work progresses. TheScrum Guidestates: "The Sprint Backlog is a plan by and for the Developers... As new work is required, the Developers add it to the Sprint Backlog. As work is performed or completed, the estimated remaining work is updated." * A:The Scrum Master facilitates, not updates. * B:Correct-the Developers manage it.