Valid CASPO-001 Dumps shared by ExamDiscuss.com for Helping Passing CASPO-001 Exam! ExamDiscuss.com now offer the newest CASPO-001 exam dumps, the ExamDiscuss.com CASPO-001 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CASPO-001 dumps with Test Engine here:
When is a Sprint finished? (Choose the best answer)
Correct Answer: C
A Sprint is a fixed-length, time-boxed event that ends when its duration expires, regardless of work completion. TheScrum Guidestates: "Sprints are the heartbeat of Scrum, where ideas are turned into value. They are fixed length events of one month or less to create consistency." The end is determined by the time- box, not by acceptance, quality standards, or task completion. * A:Product Owner acceptance occurs at Sprint Review, but doesn't define Sprint end. * B:The Definition of "Done" applies to the Increment, not the Sprint's duration. * C:Correct-the time-box dictates the end.