Valid CASPO-001 Dumps shared by ExamDiscuss.com for Helping Passing CASPO-001 Exam! ExamDiscuss.com now offer the newest CASPO-001 exam dumps, the ExamDiscuss.com CASPO-001 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CASPO-001 dumps with Test Engine here:
A Product Owner is entitled to postpone the start of a new Sprint after the conclusion of a previous Sprint for the following reason: (Choose the best answer)
Correct Answer: C
In Scrum, Sprints are continuous and fixed-length, with no gaps allowed between them. TheScrum Guide explicitly states: "A new Sprint starts immediately after the conclusion of the previous Sprint." This ensures a consistent cadence of delivery and adaptation, a cornerstone of Scrum's empirical process. Let's examine each option: * A (Not enough "Ready" items):The Product Backlog can be refined incrementally; a lack of "Ready" items doesn't justify delaying a Sprint. The team can start with what's available and refine further during the Sprint. * B (No Sprint Goal):The Sprint Goal is defined during Sprint Planning, not beforehand. Its absence pre- Sprint isn't a valid delay reason. * C:This aligns with theScrum Guide's mandate for immediate succession, making it correct. * D (QA needs more time):Scrum rejects external dependencies like a separate QAdepartment; the Developers must deliver a "Done" Increment within the Sprint. Delaying contradicts this.