Valid CASPO-001 Dumps shared by ExamDiscuss.com for Helping Passing CASPO-001 Exam! ExamDiscuss.com now offer the newest CASPO-001 exam dumps, the ExamDiscuss.com CASPO-001 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CASPO-001 dumps with Test Engine here:
When a Developers determines that it has over-committed itself for a Sprint, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer)
Correct Answer: B
TheScrum Guidestates that the Sprint Backlog is owned by the Developers, who are responsible for planning and executing the work to achieve the Sprint Goal. If they realize they've over-committed, they must adjust the Sprint Backlog. However, since the Product Owner is accountable for maximizing value and managing the Product Backlog, their involvement is critical to ensure adjustments align with value delivery and the Sprint Goal. TheScrum Guidenotes: "The Product Owner may influence the Developers by helping them understand and select trade-offs." Option A includes a non-existent "project manager" role in Scrum, making it incorrect. Option C involves stakeholders, who are not part of mid-Sprint adjustments (they provide feedback at the Sprint Review). Option D excludes the Product Owner, which is insufficient given their role. Thus, B is correct.