A project team is determining how an application will be moved to production, who the users will be, and what training is needed. Which of the following best describes what is being developed?
Correct Answer: C
This describes a transition plan (also called a release plan) because it focuses on moving a deliverable into production/go-live, defining the target audiences/users, and identifying operational training needs. The CompTIA Project+ objectives explicitly list "Develop a transition plan/release plan" and include example components such as operational training, go live, operational handoff, and identifying internal vs. external audience-all of which match the scenario.
A contingency plan is for responding to risks/issues if something goes wrong, not the standard production handover approach. A scope statement defines what work/deliverables are included and excluded, but it doesn' t detail production cutover, operational ownership, or training. A communication plan defines how information is shared (who, what, when, and through what channels), but it is not specifically the go-live and operational handoff blueprint.
So, because the team is planning deployment/move to production plus user identification and training, they are developing the transition plan.