A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan that the project team is working on?
Correct Answer: B
The team is leveraging lessons learned to create a preventive plan for avoiding issues in the upcoming project enhancement. This falls under risk management and compliance, ensuring previous failures do not repeat. Reference: CompTIA Project+ PK0-005 - Lessons Learned & Risk Avoidance;