One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?
Correct Answer: B
Obtaining approval for changes to software is crucial to ensure that the changes do not negatively impact other functionalities of the software. Approval processes typically involve a review that assesses the potential impacts of the change, which helps in mitigating risks associated with the change. Reference = The answer is based on standard project management practices and the typical use of change control processes in software development. For detailed information, please refer to the CompTIA Project+ Study Guide and other official CompTIA resources.