A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?
Correct Answer: D
This is the process of gathering information directly from the client and other stakeholders to define what needs to be done in order to deliver the project outcomes. Reference = CompTIA Project+ Study Guide1, Chapter 9: Scope Management According to the CompTIA Project+ Study Guide1, scope management is the process of defining, validating, and controlling the project scope throughout the project life cycle. Scope management involves identifying and documenting the project requirements, creating a work breakdown structure (WBS), and managing changes to the scope.