An organization is interested in purchasing a backup solution that supports the organization's goals. Which of the following concepts would specify the maximum duration that a given service can be down before impacting operations?
Correct Answer: B
The maximum duration that a given service can be down before it impacts operations is often referred to as the Recovery Time Objective (RTO).
RTO is a key consideration in any backup and disaster recovery plan, as it determines how quickly the organization needs to be able to recover from a disruption or failure. It is typically expressed in terms of time, and it helps to inform the design and implementation of the backup solution.
For example, if an organization has a critical service that must be available 24/7, it may have a very low RTO, requiring that the service be restored within a matter of minutes or even seconds.
On the other hand, if the service can be down for a longer period of time without significantly impacting operations, the organization may have a higher RTO.
When selecting a backup solution, it is important to consider the organization's RTO requirements and ensure that the solution is capable of meeting those needs. A solution that does not meet the organization's RTO requirements may not be sufficient to ensure the availability of critical services in the event of a disruption or failure.