Valid N10-008 Dumps shared by ExamDiscuss.com for Helping Passing N10-008 Exam! ExamDiscuss.com now offer the newest N10-008 exam dumps, the ExamDiscuss.com N10-008 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com N10-008 dumps with Test Engine here:
A Chief Executive Officer and a network administrator came to an agreement with a vendor to purchase new equipment for the data center. A document was drafted so all parties would be informed about the scope of the project before it started. Which of the following terms BEST describes the document used?
Correct Answer: B
What is in a project charter? A project charter is a formal short document that states a project exists and provides project managers with written authority to begin work. A project charter document describes a project to create a shared understanding of its goals, objectives and resource requirements before the project is scoped out in detail. What are the 5 elements of the project charter? What Are the Contents of a Project Charter? A project charter should always include an overview, an outline of scope, an approximate schedule, a budget estimate, anticipated risks, and key stakeholders.