After performing an initial assessment of a cloud-hosted architecture, a department wants to gain the support of upper management.
Which of the following should be presented to management?
Correct Answer: A
A project charter is a document that defines the scope, objectives, and stakeholders of a project. It also provides a high-level overview of the project's benefits, risks, assumptions, constraints, and deliverables. A project charter is used to gain the support and approval of upper management and other key stakeholders before initiating a project. A project charter is one of the outputs of the cloud assessment process, which involves evaluating the feasibility, suitability, and readiness of an organization to adopt cloud services. Reference: CompTIA Cloud Essentials+ (CLO-002) Study Guide, Chapter 4: Cloud Assessment, Section 4.1: Cloud Assessment Process, page 9712; CompTIA Cloud Essentials+ Certification Exam Objectives, Objective 4.1: Given a scenario, analyze and report the outputs of a cloud assessment, page 143