A client is adding scope to a project. Which of the following processes should be used when requesting updates or corrections to the client's systems?
Correct Answer: B
The change control board (CCB) is a committee that consists of subject matter experts and managers who decide whether to implement proposed changes to a project. The change control board is part of the change management plan, which defines the roles and processes for managing change within a team or organization. The change control board must review and approve a submission for any change request that affects the scope, schedule, budget, quality, or risks of the project. The change control board evaluates the impact and benefits of the change request and decides whether to accept, reject, or defer it.