Valid AACE-PSP Dumps shared by EduDump.com for Helping Passing AACE-PSP Exam! EduDump.com now offer the newest AACE-PSP exam dumps, the EduDump.com AACE-PSP exam questions have been updated and answers have been corrected get the newest EduDump.com AACE-PSP dumps with Test Engine here:
When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?
Correct Answer: D
* Estimating Activity Durations: The critical factors are crew size, labor hours, and the standard workday. Cost estimation is not directly required to calculate durations. * Evaluation of Options: Option A: Incorrect. Crew size is needed for productivity estimation. Option B: Incorrect. Labor hours are directly tied to durations. Option C: Incorrect. Workday hours define the available time. Option D: Correct. Cost is not directly linked to duration