Valid AACE-PSP Dumps shared by ExamDiscuss.com for Helping Passing AACE-PSP Exam! ExamDiscuss.com now offer the newest AACE-PSP exam dumps, the ExamDiscuss.com AACE-PSP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com AACE-PSP dumps with Test Engine here:
What changes to logic would eliminate Activity B from the critical path?
Correct Answer: D
* To eliminate Activity B from the critical path, its dependencies must change so that its delay no longer impacts the path's completion time. * Replacing the A → B relationship with a Finish-to-Finish with Offset (FFO) and adding an FSO (Finish-to-Start with Offset) relationship from A → C allows Activity C to proceed independently of Activity B. * Reference: PSP Study Guide, Section 2.2.4 - Relationships and Calculations, explains how relationship types can influence critical path determination.