How could the structural steel drawing delay have been prevented?
Correct Answer: B
* Preventing Structural Steel Delays: Incorporating realistic timeframes for shop drawing review and resubmittals in the baseline schedule prevents design-related delays. * Evaluation of Other Options: A: Adding time buffers does not address the root cause. C: Concurrent review may create confusion and errors. D: Switching to post-tensioned concrete is a significant design change, not a practical solution for a scheduling issue. * Verification with PSP Guidelines: Adequate review time aligns with PSP scheduling best practices (Ref: PSP Study Guide, Chapter 2B: Schedule Development and Baseline Creation).