Valid AACE-PSP Dumps shared by ExamDiscuss.com for Helping Passing AACE-PSP Exam! ExamDiscuss.com now offer the newest AACE-PSP exam dumps, the ExamDiscuss.com AACE-PSP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com AACE-PSP dumps with Test Engine here:
In its simplest form, what is the main drawback of critical path method scheduling?
Correct Answer: B
A fundamental limitation of Critical Path Method (CPM) scheduling is its assumption of unlimited resources, meaning it does not account for resource constraints when calculating schedules. Option A (backward pass) is a standard part of the CPM process. Option C is incorrect as CPM considers activity dependencies. Option D refers to flexibility in diagramming methods, not a drawback. The PSP Study Guide highlights resource constraints as a significant challenge in CPM application.