Valid LEED-AP-BD-C Dumps shared by ExamDiscuss.com for Helping Passing LEED-AP-BD-C Exam! ExamDiscuss.com now offer the newest LEED-AP-BD-C exam dumps, the ExamDiscuss.com LEED-AP-BD-C exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com LEED-AP-BD-C dumps with Test Engine here:
Based on the results of a six-hour waste stream study, the project team for a retail project plans to provide dedicated areas for four easily recyclable waste streams: cardboard, plastic, metal and paper. The project is open to the public 10 hours a day, six days a week. Which of the following actions should be the project team's top priority in order to demonstrate the minimum requirements to achieve Materials and Resources Prerequisite, Storage and Collection of Recyclables?
Correct Answer: D
Explanation According to the LEED v4 Reference Guide for Building Design and Construction, the project team must conduct a waste stream audit to identify the top five recyclable waste streams generated by the building and its occupants. The audit must cover a representative time period of a minimum of 24 hours, and must account for variations in the type and quantity of waste generated by different building uses andoperations. The project team must then provide dedicated areas for the collection and storage of these materials for recycling. The project team must also provide dedicated areas for the collection and storage of batteries, mercury-containing lamps, and electronic waste, or demonstrate that a local program is in place to properly dispose of these materials. References: * LEED v4 Reference Guide for Building Design and Construction, Materials and Resources Prerequisite: Storage and Collection of Recyclables, page 5441 * LEED v4 Credit Tutorials: Materials & Resources (BD+C/ID+C), Prerequisite: Storage and Collection of Recyclables2