Valid LEED-AP-BD-C Dumps shared by ExamDiscuss.com for Helping Passing LEED-AP-BD-C Exam! ExamDiscuss.com now offer the newest LEED-AP-BD-C exam dumps, the ExamDiscuss.com LEED-AP-BD-C exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com LEED-AP-BD-C dumps with Test Engine here:
A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?
Correct Answer: C
Explanation The correct answer is C, the Cx agent for the project must conduct or oversee the Cx of the PV system. According to the LEED v4 Reference Guide for Building Design and Construction, the Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification, requires that all energy-related systems, including renewable energy systems such as PV, be commissioned by an independent commissioning agent (CxA) or a qualified member of the project team who reports to the owner.The CxA or the qualified team member must perform or oversee all commissioning activities, including developing a commissioning plan, reviewing design documents and submittals, verifying installation and performance, and preparing a commissioning report12References:1: LEED v4 Reference Guide for Building Design and Construction, Energy and Atmosphere Prerequisite: Fundamental Commissioning and Verification, page 562.2: LEED v4 Reference Guide for Building Design and Construction, Glossary, page 1020.