Valid OG0-092 Dumps shared by ExamDiscuss.com for Helping Passing OG0-092 Exam! ExamDiscuss.com now offer the newest OG0-092 exam dumps, the ExamDiscuss.com OG0-092 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com OG0-092 dumps with Test Engine here:
Scenario: Please read this scenario prior to answering the question You are the Lead Enterprise Architect in a company that specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. The company has manufacturing facilities located in Illinois, Nebraska, and Manitoba. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturer's design specifications. Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and improved blade longevity. The company has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded. The company has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program. TOGAF 9 and its Architecture Development Method (ADM) are used to develop the automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies. Recently, a pilot architecture project was completed at a single location that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Architecture Board approved the plan for immediate implementation at each plant. Architecture Contracts have been developed that detail the work needed to implement and deploy the new Automated Test System controller for each location. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each location to ensure consistency. Refer to the Scenario You have been asked to recommend the best approach to address the Chief Engineer's concern. Based on TOGAF 9, which of the following is the best answer?