You are the Lead Architect for a firm that manufactures ball bearings used in industrial equipment applications. They have manufacturing operations in several cities in the United States, Germany, and the United Kingdom.
The firm has traditionally allowed each manufacturing plant to drive its own production planning systems.
Each plant has its own custom Materials Requirements Planning, Master Production Scheduling, Bill of Materials, and Shop Floor Control systems.
"Just In Time" manufacturing techniques are used to minimize wastes caused by excessive inventory and work in process. The increasingly competitive business environment has compelled the firm to improve its business capability to be more responsive to the needs of industrial customers. To support this capability, the firm has decided to implement an Enterprise Resource Planning (ERP) solution that will enable it to better coordinate its manufacturing capacity to match the demands for its products across all plants. In addition, there are also new European regulations coming into force to which their manufacturing processes must conform in the next six months.
As part of the implementation process, the Enterprise Architecture (EA) department has begun to implement an architecture process based on TOGAF 9. The CIO is the sponsor of the activity. The Chief Architect has directed that the program should include formal modeling using the Architecture Content Framework and the TOGAF Content Metamodel. This will enable support for the architecture tooling that the firm uses for its EA program.
The Chief Architect has stated that in order to model the complex manufacturing process it will be necessary to model processes that are event-driven. Also, in order to consolidate applications across several data centers it will be necessary to model the location of IT assets. In particular, the end goal is to have the single ERP application running in a single data center.
Currently the project is in the Preliminary Phase, and the architects are tailoring the Architecture Development Method (ADM) and Architecture Content Framework to fit into the corporate environment.
Refer to the Scenario
You have been asked to recommend a response to the Chief Architect's request to tailor the TOGAF Content Metamodel.
Based on TOGAF 9, which of the following is the best answer?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (65q)
Question 1: UTrack Transports is a strong UK logistics company. The head...
Question 2: An international Insurance company has grown with little con...
Question 3: TotalComms is a telecommunications company formed from the m...
Question 4: Scenario: MegaMart Case Study Title (Case Study): MegaMart i...
Question 5: Scenario: Please read this scenario prior to answering the Q...
Question 6: MightyGears produces components for the Car industry. Driven...
Question 7: Scenario: Please read this scenario prior to answering the Q...
Question 8: Scenario: Armstrong Defense Industries Please read this scen...
Question 9: Scenario: St. Croix Consulting Please read this scenario pri...
Question 10: Chiamin Metals is a leading world-wide manufacturer for cont...
Question 11: Scenario: Vittronics Ltd. Please read this scenario prior to...
Question 12: Scenario: Glacier Ridge LLC Please read this scenario prior ...
Question 13: TP Banking is a strong financial institute with a well-known...
Question 14: Worldwide Mobile is a mobile telecommunications company form...
Question 15: Scenario Please read this scenario prior to answering the qu...
Question 16: Scenario: Eight Twelve Eight Twelve has retail outlets throu...
Question 17: ARTI Dimensioning is a multinational that operates productio...
Question 18: Scenario: Vittronics Ltd. Please read this scenario prior to...
Question 19: FreshFruit Int. is an online American grocer. The Executive ...
Question 20: Patterns &amp; Co. is introducing a Commercial Off-the-Shelf...
Question 21: Scenario: Please read this scenario prior to answering the q...
Question 22: Scenario Please read this scenario prior to answering the qu...
Question 23: RIG Networks, a global network supplier is implementing a ma...
Question 24: Scenario: AGEX Inc. Please read this scenario prior to answe...
Question 25: Scenario Please read this scenario prior to answering the qu...
Question 26: Scenario: Raxlon Inc. Case Study Title (Case Study): Raxlon ...
Question 27: Scenario: AutoComp Corporation AutoComp Corporation produces...
Question 28: Scenario: AGEX Inc. Please read this scenario prior to answe...
Question 29: McKinley Rockets is an enterprise that employs 20,000 men an...
Question 30: Scenario: Please read this scenario prior to answering the Q...
Question 31: Scenario: Please read this scenario prior to answering the Q...
Question 32: Scenario Please read this scenario prior to answering the qu...
Question 33: Scenario Please read this scenario prior to answering the qu...
Question 34: Scenario: Rollins Manufacturing Please read this scenario pr...
Question 35: Scenario Please read this scenario prior to answering the qu...
Question 36: Please read this scenario prior to answering the question Yo...
Question 37: Please read this scenario prior to answering the question Yo...
Question 38: Scenario: Please read this scenario prior to answering the q...
Question 39: Carter Woods, a global furniture firm, wants to improve the ...
Question 40: Scenario: Sollace Manufacturing Please read this scenario pr...
Question 41: Scenario: Please read this scenario prior to answering the Q...
Question 42: Scenario: Global Mobile 1 Please read this scenario prior to...
Question 43: Scenario: Please read this scenario prior to answering the Q...
Question 44: SureFlight Air Carrier has received approval for the acquisi...
Question 45: Scenario: Please read this scenario prior to answering the Q...
Question 46: Scenario: Please read this scenario prior to answering the Q...
Question 47: Scenario Please read this scenario prior to answering the qu...
Question 48: Scenario: Florian Flowers BV Please read this scenario prior...
Question 49: Scenario Please read this scenario prior to answering the qu...
Question 50: Scenario Please read this scenario prior to answering the qu...
Question 51: Scenario Please read this scenario prior to answering the qu...
Question 52: Scenario: Zephyr Enterprises Please read this scenario prior...
Question 53: Scenario: Marona Inc. Marona Inc is a Fortune 500 Enterprise...
Question 54: Scenario: Summer Seeds BV Please read this scenario prior to...
Question 55: Scenario: Please read this scenario prior to answering the q...
Question 56: Scenario Please read this scenario prior to answering the qu...
Question 57: Scenario: Please read this scenario prior to answering the Q...
Question 58: Scenario Please read this scenario prior to answering the qu...
Question 59: Scenario Please read this scenario prior to answering the qu...
Question 60: Magic Wand Corporation manufactures a range of equipment use...
Question 61: Scenario Please read this scenario prior to answering the qu...
Question 62: Dante Manufacturing is a big supplier in the automotive indu...
Question 63: Scenario: Zephyr Enterprises Please read this scenario prior...
Question 64: Scenario: Please read this scenario prior to answering the Q...
Question 65: Scenario: Rollins Manufacturing Please read this scenario pr...