Within the same Kanban system, Work in Progress (WIP), is NOT a leading indicator for: (choose the best answer)
Correct Answer: B
Within the same Kanban system, Work in Progress (WIP) is not a leading indicator for "Story points delivered." While WIP can influence throughput and cycle time, it does not directly correlate with story points delivered, as story points are a measure of effort or complexity rather than flow. The number of story points delivered is not directly influenced by the current WIP levels