What is the flow metric used to forecast how many items will be done for a date?
Correct Answer: D
Throughput, which measures the number of items completed over a specific period, is essential for forecasting future delivery rates. By analyzing historical throughput data, Scrum Teams using Kanban can make informed predictions about how many items they can complete by a given date. Reference: The Kanban Guide for Scrum Teams.