When using Kanban in a Scrum environment, some resistance toward introducing Work in Progress (WIP) Limits may be encountered. What is an alternative to introducing WIP Limits in Kanban?
Correct Answer: A
Although WIP limits are central to Kanban, enhancing visualization and communication through Kanban boards can be a way to ease into WIP limits gradually. This alternative fosters transparency and alignment without directly imposing WIP constraints, which can be beneficial for teams adjusting to Kanban practices. Reference: The Kanban Guide for Scrum Teams.