Valid Certified-Business-Analyst Dumps shared by ExamDiscuss.com for Helping Passing Certified-Business-Analyst Exam! ExamDiscuss.com now offer the newest Certified-Business-Analyst exam dumps, the ExamDiscuss.com Certified-Business-Analyst exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com Certified-Business-Analyst dumps with Test Engine here:
Northern Trail Outfitters is undergoing a Service Cloud implementation and has decided to use the Scrum methodology for the implementation. A business analyst (BA) received an urgent, high-priority change request m the middle of a sprint. Which step should the BA take next?
Correct Answer: C
The step that business analyst should take next after receiving urgent high-priority change request middle sprint add change request backlog prioritized next sprint backlog list user stories features enhancements bugs fixes need done project backlog prioritized based importance urgency value risk etc adding change request backlog prioritized next sprint helps maintain scope integrity current sprint avoid disrupting ongoing work respect sprint goal commitment. De-prioritizing some user stories and adding change request current sprint not step that business analyst should take next after receiving urgent high-priority change request middle sprint de-prioritizing some user stories adding change request current sprint helps accommodate new requirement but compromises existing work disrupts sprint goal commitment de-prioritizing some user stories adding change request current sprint should only done exceptional cases after consulting whole team stakeholders sponsors. Beginning working change request soon team has capacity not step that business analyst should take next after receiving urgent high-priority change request middle sprint beginning working change request soon team has capacity helps address new requirement but compromises existing work disrupts sprint goal commitment beginning working change request soon team has capacity should only done exceptional cases after consulting whole team stakeholders sponsors. References: https://trailhead.salesforce.com/en/content/learn/modules/agile-project-management/agile-project-management-s
Recent Comments (The most recent comments are at the top.)
Abdennour Benhamida - Aug 05, 2024
The answer is A, you have it on another dump as well, and previous comment summerizes the thing perfectly to why it's A
Allan - Jul 12, 2024
The correct answer should be "A" right?
The step that business analyst should take next after receiving urgent high-priority change request middle sprint add change request backlog prioritized next sprint backlog list user stories features enhancements bugs fixes need done project backlog prioritized based importance urgency value risk etc adding change request backlog prioritized next sprint helps maintain scope integrity current sprint avoid disrupting ongoing work respect sprint goal commitment.
Recent Comments (The most recent comments are at the top.)
The answer is A, you have it on another dump as well, and previous comment summerizes the thing perfectly to why it's A
The correct answer should be "A" right?
The step that business analyst should take next after receiving urgent high-priority change request middle sprint add change request backlog prioritized next sprint backlog list user stories features enhancements bugs fixes need done project backlog prioritized based importance urgency value risk etc adding change request backlog prioritized next sprint helps maintain scope integrity current sprint avoid disrupting ongoing work respect sprint goal commitment.