Which of the following considerations apply when determining the project methodology? Note: There are 3 correct answers to this question.
Correct Answer: A,C,D
* A is correct because implementation fit is one of the considerations that apply when determining the project methodology. It means that the project methodology should match the type and scope of the implementation, such as cloud, on-premise, hybrid, or mixed scenarios.
* C is correct because organizational fit is one of the considerations that apply when determining the project methodology. It means that the project methodology should suit the culture and maturity of the organization, such as its readiness for change, agility, and innovation.
* D is correct because project fit is one of the considerations that apply when determining the project methodology. It means that the project methodology should align with the characteristics and constraints of the project, such as its size, complexity, duration, and budget. Verified References:
* : SAP Activate Methodology for SAP S/4HANA Cloud, page 13