Valid C_ACT_2403 Dumps shared by ExamDiscuss.com for Helping Passing C_ACT_2403 Exam! ExamDiscuss.com now offer the newest C_ACT_2403 exam dumps, the ExamDiscuss.com C_ACT_2403 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_ACT_2403 dumps with Test Engine here:
What criteria does the product owner use to sequence the backlog?Note: There are 2 correct answers to this question.
Correct Answer: A,C
* A is correct because technical dependencies are one of the criteria that the product owner uses to sequence the backlog. Technical dependencies are the relationships between user stories that affect their order of implementation. For example, some user stories may require other user stories to be completed first, or some user stories may have a common prerequisite or constraint. * C is correct because business priority are one of the criteria that the product owner uses to sequence the backlog. Business priority is the measure of how important and valuable a user story is for the customer and the stakeholders. The product owner decides which user stories are more urgent and beneficial, and places them higher in the backlog. Verified References: * : Product Backlog