Valid ITIL-4-Practitioner-Deployment-Management Dumps shared by ExamDiscuss.com for Helping Passing ITIL-4-Practitioner-Deployment-Management Exam! ExamDiscuss.com now offer the newest ITIL-4-Practitioner-Deployment-Management exam dumps, the ExamDiscuss.com ITIL-4-Practitioner-Deployment-Management exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com ITIL-4-Practitioner-Deployment-Management dumps with Test Engine here:
[Apply Deployment Management Processes] What key output of the 'deployment model development and improvement' process can be used to trigger implementation of a newly updated deployment model?
Correct Answer: B
In ITIL 4, the deployment model development and improvement process involves creating or refining models to enhance deployment effectiveness. Implementing a newly updated deployment model typically requires formal authorization and coordination, which is achieved through a change request (Option B). A change request initiates the process to assess, approve, and execute the model update in a controlled manner, ensuring alignment with organizational governance and other practices like change enablement. Option A (Lessons learned): Incorrect, as lessons learned are an output for improving future processes, not a trigger for implementing a new model. Option B (Change request): Correct, as a change request is the formal mechanism to propose and implement a new or updated deployment model, per ITIL 4's integration with change enablement. Option C (Updated knowledge management articles): Incorrect, as knowledge articles support documentation and training but do not trigger implementation. Option D (Deployment review reports): Incorrect, as review reports provide insights or feedback, not the authorization needed to implement a model.