Valid PRINCE2-Practitioner Dumps shared by ExamDiscuss.com for Helping Passing PRINCE2-Practitioner Exam! ExamDiscuss.com now offer the newest PRINCE2-Practitioner exam dumps, the ExamDiscuss.com PRINCE2-Practitioner exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PRINCE2-Practitioner dumps with Test Engine here:
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions. The Stage Plan for stage 3 has been produced. The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager. None of the E500 change budget has been used to date and this is available for the stage. Which 2 statements apply to the Budgets section?