<< Prev Question Next Question >>

Question 153/271

The project is approaching the end of stage 3, and stage 4 is being planned as part of the 'managing a stage boundary' process.
Which action should the project manager carry out as part of the 'update the project plan' activity?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (271q)
1 commentQuestion 1: It is now late October and the project is in stage 3. The la...
Question 2: Additional Information Chief Executive Officer (CEO): He sta...
Question 3: Scenario A central government department, the Ministry of Fo...
Question 4: Which 2 statements should be recorded under the Expected dis...
Question 5: Which 2 statements should be recorded under the Timescale he...
Question 6: Scenario Additional Information Chief Executive Officer (CEO...
Question 7: Scenario Additional Information Product Description (Exhibit...
Question 8: Scenario Additional Information Product Description (Exhibit...
Question 9: Scenario: Techniques, processes and procedures 1. Any threat...
Question 10: M1ich statement is an appropriate entry for the outline Busi...
Question 11: During Executing a Work package, specialist products are cre...
Question 12: Scenario Additional Information Extract from the Communicati...
Question 13: The executive has set the following tolerances for stage 2: ...
Question 14: Which 2 alternative actions apply to the proposed user assur...
1 commentQuestion 15: Which of the following reports does not contain any informat...
Question 16: Scenario Additional Information Product Description (Exhibit...
Question 17: Project Scenario - Health and Safety Training Project: ABC C...
Question 18: Project Scenario - Health and Safety Training Project: ABC C...
Question 19: Scenario Additional Information Product Description (Exhibit...
Question 20: The project is in stage 3. Zero time tolerance has been give...
Question 21: Which 2 statements should be recorded under the Timescale he...
Question 22: Which 2 statements correctly define a Business Case risk whi...
Question 23: Additional Information (Exhibit) Further information on some...
Question 24: Scenario Additional Information Chief Executive Officer (CEO...
Question 25: The executive has set the following tolerances for stage 2: ...
Question 26: While producing the Team Plan to deliver the agreed Work Pac...
Question 27: Which of the following statements would NOT be included in t...
Question 28: Which management product defines the detailed nature, purpos...
1 commentQuestion 29: If the Project Board are too busy to authorize all change re...
Question 30: Project Scenario - Health and Safety Training Project: ABC C...
Question 31: ABC Company has a standard course development model with fou...
Question 32: Which 2 alternative actions apply to the proposed Senior Sup...
Question 33: Scenario Extract from the Project Product Description (with ...
Question 34: Using the Project Scenario and the Extract from Stage Plan f...
Question 35: While capturing previous lessons, the Project Manager discov...
Question 36: It is now late October and the project is in stage 3. The la...
Question 37: Additional Information Product Description (Exhibit) Quality...
Question 38: Scenario: Techniques, processes and procedures 1. Any threat...
Question 39: Which 2 statements should be recorded under the Reasons head...
Question 40: Using the Project Scenario and the Extract from Stage Plan f...
Question 41: During which process would the stage tolerances be set?...
Question 42: The project board has asked for highlight reports every six ...
1 commentQuestion 43: CLOSING A PROJECT Benefits relating to income and business r...
Question 44: Which of the following principles uses Product Descriptions ...
Question 45: Without a Risk Register how can project risks, the progress ...
Question 46: Extract from the Project Product Description (with errors) (...
Question 47: Project Scenario - Health and Safety Training Project: ABC C...
Question 48: Which role is responsible for providing the customer's quali...
Question 49: Which is a correctly defined acceptance criterion for the se...
Question 50: Which product should show that without the calendar the comp...
Question 51: Scenario Additional Information (Exhibit) Further informatio...
Question 52: INITIATING A PROJECT Here are three items of information rel...
Question 53: Additional Information During the initiation stage the Proje...
Question 54: It is now late October and the project is in stage 3. The la...
Question 55: Although it is not specified in the current corporate brandi...
Question 56: Project Scenario - Health and Safety Training Project: ABC C...
Question 57: While deciding on how the work of the project should be appr...
Question 58: Project Scenario - Health and Safety Training Project: ABC C...
Question 59: Which principle is supported by the activity Evaluate the Pr...
Question 60: Project Scenario - Health and Safety Training Project: ABC C...
Question 61: Scenario Additional Information (Exhibit) Further informatio...
Question 62: The project is at the end of stage 4. The project manager ha...
Question 63: The project is now in stage 2. The Project Manager has heard...
Question 64: Scenario Additional Information Extract from the Communicati...
Question 65: Scenario Additional Information Extract from the Communicati...
Question 66: Which 2 statements should be recorded under the Costs headin...
Question 67: Who is responsible for confirming stage and project progress...
Question 68: The project is part of a program to increase the number of A...
Question 69: The project board has asked for highlight reports every six ...
Question 70: It is now late October and the project is in stage 3. The la...
Question 71: HOTSPOT The Calendar project was delivered as originally pla...
Question 72: Which project controls should be established for the Outsour...
Question 73: The project is part of a program to increase the number of A...
Question 74: ABC Company has a standard course development model with fou...
Question 75: The Manage by Exception principle sets tolerances for six ar...
Question 76: Using the Project Scenario and the Extract from Stage Plan f...
Question 77: It is now late October and the project is in stage 3. The la...
Question 78: Additional Information Extract from the Communication Manage...
Question 79: This question provides a number of changes which may or may ...
Question 80: Checkpoint reports are being produced monthly. A week after ...
Question 81: Scenario Product Summary A list of customers will be collate...
Question 82: Which other management product is created when the Business ...
Question 83: Project Scenario - Health and Safety Training Project: ABC C...
1 commentQuestion 84: Which of the following statements are True: 1.Quality manage...
Question 85: Additional Information Product Description (Exhibit) Quality...
Question 86: Which statement applies to the Records section?...
Question 87: Which of the following should NOT be included in the busines...
Question 88: Additional Information Chief Executive Officer (CEO): He sta...
Question 89: There is no project schedule in the Project Initiation Docum...
Question 90: In the PRINCE2 Quality review technique, who would most like...
Question 91: Scenario Additional Information During the initiation stage ...
Question 92: Project Scenario - Health and Safety Training Project: ABC C...
Question 93: HOTSPOT Scenario A photographer from Portraits Ltd, a profes...
Question 94: Scenario Additional Information Product Description (Exhibit...
Question 95: Scenario Additional Information (Exhibit) Further informatio...
Question 96: Scenario A photographer from Portraits Ltd, a professional p...
Question 97: MANAGING PRODUCT DELIVERY The team manager for the productio...
Question 98: Which 2 statements should be recorded under the Major risks ...
Question 99: Which principle is central to the quality theme and provides...
1 commentQuestion 100: Which of the following risk responses can be used for either...
Question 101: Project Scenario - Health and Safety Training Project: ABC C...
Question 102: Which project controls should be established for the Outsour...
Question 103: Scenario Additional Information Chief Executive Officer (CEO...
Question 104: Additional Information Product Description (Exhibit) Quality...
Question 105: Which role is responsible for providing the customer's quali...
Question 106: One of the senior managers of the company that is developing...
Question 107: Scenario Additional Information Product Description (Exhibit...
Question 108: HOTSPOT Column 1 is a list of entries from the Daily Log tha...
Question 109: Without a Risk Register how can project risks, the progress ...
Question 110: Scenario Additional Information Product Description (Exhibit...
Question 111: If Project tolerances were threatened, who needs to be notif...
Question 112: Which 2 statements should be recorded under the Reasons head...
Question 113: The project is now in stage 2. The Project Manager has heard...
Question 114: Scenario: Techniques, processes and procedures 1. Any threat...
Question 115: This question provides a number of changes which may or may ...
Question 116: Project Scenario - Health and Safety Training Project: ABC C...
Question 117: Scenario Product Summary A list of customers will be collate...
Question 118: During stage 1 the level of performance expected from the se...
Question 119: Using the Project Scenario and the Extract from Stage Plan f...
Question 120: Product Summary A list of customers will be collated. This w...
Question 121: Using the Project Scenario and the Extract from Stage Plan f...
Question 122: Whilst identifying the mailing costs for the calendars the P...
Question 123: Project Scenario Calendar Project (Note: The companies and p...
Question 124: Two weeks after starting work the Team Manager noticed that ...
Question 125: Which of the following management products ARE updated as pa...
Question 126: The executive identified that there would be a benefit to th...
Question 127: During which of the following activities is the Project Prod...
Question 128: Starting Up a project is triggered by which of the following...
Question 129: Which of the following statements best describes what a risk...
Question 130: Scenario Additional Information During the initiation stage ...
Question 131: Which product should show that if anybody has any remaining ...
Question 132: Scenario: The Ministry of Food Hygiene (MFH) has a quality m...
Question 133: The senior user is concerned that the trainers' limited avai...
Question 134: Which is a correctly defined acceptance criterion for the tr...
Question 135: The delivery of the pilot courses has been split into two se...
Question 136: Additional Information Product Description (Exhibit) Quality...
Question 137: Additional Information Extract from the Communication Manage...
Question 138: Scenario Additional Information During the initiation stage ...
Question 139: Additional Information Extract from the Communication Manage...
Question 140: Scenario A photographer from Portraits Ltd, a professional p...
Question 141: Which 2 statements explain why the CEO should be appointed a...
Question 142: Which of the following statements is False regarding the Ris...
Question 143: Scenario A photographer from Portraits Ltd, a professional p...
Question 144: The project is part of a program to develop more training co...
Question 145: Which 2 alternative actions apply to the proposed Executive ...
Question 146: Which of the following is False? A Successful project manage...
Question 147: The executive identified that there would be a benefit to th...
Question 148: Scenario Additional Information Product Description (Exhibit...
Question 149: Which of the following principles describes this statement?"...
Question 150: Who is responsible for confirming stage and project progress...
Question 151: M1ich statement is an appropriate entry for the outline Busi...
Question 152: Towards the end of stage 2, the stage 3 plan is being prepar...
Question 153: The project is approaching the end of stage 3, and stage 4 i...
Question 154: Additional Information Product Description (Exhibit) Quality...
Question 155: Who is responsible for committing user resources to the proj...
Question 156: The team member collating the list of customers has now fore...
Question 157: No Benefits Review Plan has been developed. Where should the...
Question 158: Scenario Additional Information During the initiation stage ...
Question 159: Who is responsible for committing user resources to the proj...
Question 160: Scenario A central government department, the Ministry of Fo...
Question 161: Which project controls should be established for the Outsour...
Question 162: Additional Information A photographer from Portraits Ltd, a ...
Question 163: When considering the business options in the business case, ...
Question 164: Scenario Additional Information Product Description (Exhibit...
Question 165: The project is at the start of stage 3, and there will be si...
Question 166: Which of the following statements would NOT be included in t...
Question 167: Which 2 statements explain why the Sales Manager should be a...
Question 168: A construction company that is one of ABC Company's key clie...
Question 169: Which of the following is NOT an objective of Initiating a P...
Question 170: Based on lessons from previous projects that used the ABC Co...
Question 171: This question provides a number of changes which may or may ...
Question 172: Which of the following statements is TRUE with regard to exp...
Question 173: Scenario Product Summary A list of customers will be collate...
Question 174: Which 2 statements explain why Central Records should be app...
Question 175: Project Scenario - Health and Safety Training Project: ABC C...
Question 176: Scenario: Techniques, processes and procedures 1. Any threat...
Question 177: If Project tolerances were threatened, who needs to be notif...
Question 178: Which of the following statements is true of the business in...
Question 179: The project is now in stage 2. The Project Manager has heard...
Question 180: Scenario A photographer from Portraits Ltd, a professional p...
Question 181: Who is responsible for ensuring that Communication Managemen...
Question 182: During stage 2, if the Project Manager decides to recommend ...
Question 183: Scenario Additional Information Chief Executive Officer (CEO...
Question 184: It is now late October and the project is in stage 3. The la...
Question 185: During stage 2, if the Project Manager decides to recommend ...
Question 186: Which statement is an appropriate entry for the outline Busi...
Question 187: Scenario Additional Information Chief Executive Officer (CEO...
Question 188: Which statement applies to the Introduction section?...
Question 189: Which 2 alternative actions apply to the proposed user assur...
Question 190: The Team Manager has received notification that the new hard...
Question 191: Scenario Product Summary A list of customers will be collate...
Question 192: Scenario Additional Information Product Description (Exhibit...
Question 193: At the end of stage 2, an external consultant responsible fo...
Question 194: Scenario A photographer from Portraits Ltd, a professional p...
Question 195: Project Scenario - Health and Safety Training Project: ABC C...
Question 196: Which statement is an appropriate entry for the project appr...
Question 197: There is no Project Brief. How can there be a common underst...
Question 198: Scenario Additional Information Extract from the Communicati...
Question 199: It is now late October and the project is in stage 3. The la...
Question 200: The delivery of the pilot courses has been split into two se...
Question 201: Scenario Additional Information Chief Executive Officer (CEO...
Question 202: During previous projects, stakeholders became confused when ...
Question 203: Project Scenario Calendar Project (Note: The companies and p...
Question 204: Project Scenario - Health and Safety Training Project: ABC C...
Question 205: Scenario Additional Information Extract from the Communicati...
Question 206: Additional Information Chief Executive Officer (CEO): He sta...
Question 207: Which product should show that the project has been closed p...
Question 208: The Health and Safety Training Project is closing as planned...
Question 209: HOTSPOT Scenario A photographer from Portraits Ltd, a profes...
Question 210: Project Scenario - Health and Safety Training Project: ABC C...
Question 211: HOTSPOT Scenario: Techniques, processes and procedures 1. An...
Question 212: Additional Information Extract from the Communication Manage...
Question 213: Scenario Additional Information During the initiation stage ...
Question 214: Project Scenario - Health and Safety Training Project: ABC C...
Question 215: The government agency held a seminar for training organizati...
Question 216: Extract from the Project Product Description (with errors) (...
Question 217: At the end of stage 2, an external consultant responsible fo...
Question 218: Which 2 statements should be recorded under the Expected ben...
Question 219: Scenario: The Ministry of Food Hygiene (MFH) has a quality m...
Question 220: Project Scenario - Health and Safety Training Project: ABC C...
Question 221: The project is using PRINCE2's recommended risk management p...
Question 222: Scenario Additional Information Chief Executive Officer (CEO...
Question 223: MANAGING PRODUCT DELIVERY The team manager for the productio...
Question 224: Use the 'Additional Information' in the Scenario Booklet to ...
Question 225: Which statement is an appropriate entry for the Lessons Log?...
Question 226: During which of the following activities is the Project Prod...
Question 227: This question provides a number of changes which may or may ...
Question 228: Project Scenario Calendar Project (Note: The companies and p...
Question 229: The project is now in stage 2. The Project Manager has heard...
Question 230: Who would be responsible for maintaining the Configuration I...
Question 231: Scenario Additional Information Extract from the Communicati...
Question 232: Scenario Additional Information During the initiation stage ...
Question 233: Which management product defines the detailed nature, purpos...
Question 234: Additional Information Extract from the Communication Manage...
Question 235: Project Scenario - Health and Safety Training Project: ABC C...
Question 236: It is now late October and the project is in stage 3. The la...
Question 237: Column 1 is a list of entries from the Daily Log that occurr...
Question 238: The project is approaching the end of stage 4 and all work w...
Question 239: MANAGING A STAGE BOUNDARY The project is approaching the end...
Question 240: HOTSPOT Project Scenario Calendar Project (Note: The compani...
Question 241: The project is using PRINCE2's recommended risk management p...
Question 242: Scenario A central government department, the Ministry of Fo...
Question 243: Although it is not specified in the current corporate brandi...
Question 244: This question provides a number of changes which may or may ...
Question 245: Which statement is an appropriate entry for the project appr...
Question 246: Product Summary A list of customers will be collated. This w...
Question 247: Scenario A central government department, the Ministry of Fo...
Question 248: The executive has set the following tolerances for stage 2: ...
Question 249: Which statement applies to the Introduction section?...
Question 250: Scenario Additional Information (Exhibit) Further informatio...
Question 251: While deciding on how the work of the project should be appr...
Question 252: Who is responsible for the initial creation of the Configura...
Question 253: The Health and Safety Training Project is closing as planned...
Question 254: A quality review of the 'marketing materials' has started. T...
Question 255: The project is in stage 2. The project manager is reviewing ...
Question 256: An external consultant has signed a contract and agreed a wo...
Question 257: STARTING UP A PROJECT Here are three actions carried out by ...
Question 258: A change authority has been appointed for the project. Durin...
Question 259: Which statement is TRUE with regard to technical stages?...
Question 260: Additional Information Extract from the Communication Manage...
Question 261: Which statement is TRUE with regard to technical stages?...
Question 262: HOTSPOT Scenario A photographer from Portraits Ltd, a profes...
Question 263: The 'classroom-based training materials' will be used as the...
Question 264: This question provides a number of changes which may or may ...
Question 265: None of the reviewers have proof-reading skills....
Question 266: Who is responsible for ensuring that the value-for-money sol...
Question 267: Project Scenario - Health and Safety Training Project: ABC C...
Question 268: During stage 3, project costs are increasing but there will ...
Question 269: Which product should show that the project has been closed p...
Question 270: Scenario Additional Information (Exhibit) Further informatio...
Question 271: HOTSPOT Product Summary A list of customers will be collated...