Scenario
Additional Information

Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed supplier assurance for this project?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (271q)
1 commentQuestion 1: It is now late October and the project is in stage 3. The la...
Question 2: Additional Information Chief Executive Officer (CEO): He sta...
Question 3: Scenario A central government department, the Ministry of Fo...
Question 4: Which 2 statements should be recorded under the Expected dis...
Question 5: Which 2 statements should be recorded under the Timescale he...
Question 6: Scenario Additional Information Chief Executive Officer (CEO...
Question 7: Scenario Additional Information Product Description (Exhibit...
Question 8: Scenario Additional Information Product Description (Exhibit...
Question 9: Scenario: Techniques, processes and procedures 1. Any threat...
Question 10: M1ich statement is an appropriate entry for the outline Busi...
Question 11: During Executing a Work package, specialist products are cre...
Question 12: Scenario Additional Information Extract from the Communicati...
Question 13: The executive has set the following tolerances for stage 2: ...
Question 14: Which 2 alternative actions apply to the proposed user assur...
1 commentQuestion 15: Which of the following reports does not contain any informat...
Question 16: Scenario Additional Information Product Description (Exhibit...
Question 17: Project Scenario - Health and Safety Training Project: ABC C...
Question 18: Project Scenario - Health and Safety Training Project: ABC C...
Question 19: Scenario Additional Information Product Description (Exhibit...
Question 20: The project is in stage 3. Zero time tolerance has been give...
Question 21: Which 2 statements should be recorded under the Timescale he...
Question 22: Which 2 statements correctly define a Business Case risk whi...
Question 23: Additional Information (Exhibit) Further information on some...
Question 24: Scenario Additional Information Chief Executive Officer (CEO...
Question 25: The executive has set the following tolerances for stage 2: ...
Question 26: While producing the Team Plan to deliver the agreed Work Pac...
Question 27: Which of the following statements would NOT be included in t...
Question 28: Which management product defines the detailed nature, purpos...
1 commentQuestion 29: If the Project Board are too busy to authorize all change re...
Question 30: Project Scenario - Health and Safety Training Project: ABC C...
Question 31: ABC Company has a standard course development model with fou...
Question 32: Which 2 alternative actions apply to the proposed Senior Sup...
Question 33: Scenario Extract from the Project Product Description (with ...
Question 34: Using the Project Scenario and the Extract from Stage Plan f...
Question 35: While capturing previous lessons, the Project Manager discov...
Question 36: It is now late October and the project is in stage 3. The la...
Question 37: Additional Information Product Description (Exhibit) Quality...
Question 38: Scenario: Techniques, processes and procedures 1. Any threat...
Question 39: Which 2 statements should be recorded under the Reasons head...
Question 40: Using the Project Scenario and the Extract from Stage Plan f...
Question 41: During which process would the stage tolerances be set?...
Question 42: The project board has asked for highlight reports every six ...
1 commentQuestion 43: CLOSING A PROJECT Benefits relating to income and business r...
Question 44: Which of the following principles uses Product Descriptions ...
Question 45: Without a Risk Register how can project risks, the progress ...
Question 46: Extract from the Project Product Description (with errors) (...
Question 47: Project Scenario - Health and Safety Training Project: ABC C...
Question 48: Which role is responsible for providing the customer's quali...
Question 49: Which is a correctly defined acceptance criterion for the se...
Question 50: Which product should show that without the calendar the comp...
Question 51: Scenario Additional Information (Exhibit) Further informatio...
Question 52: INITIATING A PROJECT Here are three items of information rel...
Question 53: Additional Information During the initiation stage the Proje...
Question 54: It is now late October and the project is in stage 3. The la...
Question 55: Although it is not specified in the current corporate brandi...
Question 56: Project Scenario - Health and Safety Training Project: ABC C...
Question 57: While deciding on how the work of the project should be appr...
Question 58: Project Scenario - Health and Safety Training Project: ABC C...
Question 59: Which principle is supported by the activity Evaluate the Pr...
Question 60: Project Scenario - Health and Safety Training Project: ABC C...
Question 61: Scenario Additional Information (Exhibit) Further informatio...
Question 62: The project is at the end of stage 4. The project manager ha...
Question 63: The project is now in stage 2. The Project Manager has heard...
Question 64: Scenario Additional Information Extract from the Communicati...
Question 65: Scenario Additional Information Extract from the Communicati...
Question 66: Which 2 statements should be recorded under the Costs headin...
Question 67: Who is responsible for confirming stage and project progress...
Question 68: The project is part of a program to increase the number of A...
Question 69: The project board has asked for highlight reports every six ...
Question 70: It is now late October and the project is in stage 3. The la...
Question 71: HOTSPOT The Calendar project was delivered as originally pla...
Question 72: Which project controls should be established for the Outsour...
Question 73: The project is part of a program to increase the number of A...
Question 74: ABC Company has a standard course development model with fou...
Question 75: The Manage by Exception principle sets tolerances for six ar...
Question 76: Using the Project Scenario and the Extract from Stage Plan f...
Question 77: It is now late October and the project is in stage 3. The la...
Question 78: Additional Information Extract from the Communication Manage...
Question 79: This question provides a number of changes which may or may ...
Question 80: Checkpoint reports are being produced monthly. A week after ...
Question 81: Scenario Product Summary A list of customers will be collate...
Question 82: Which other management product is created when the Business ...
Question 83: Project Scenario - Health and Safety Training Project: ABC C...
1 commentQuestion 84: Which of the following statements are True: 1.Quality manage...
Question 85: Additional Information Product Description (Exhibit) Quality...
Question 86: Which statement applies to the Records section?...
Question 87: Which of the following should NOT be included in the busines...
Question 88: Additional Information Chief Executive Officer (CEO): He sta...
Question 89: There is no project schedule in the Project Initiation Docum...
Question 90: In the PRINCE2 Quality review technique, who would most like...
Question 91: Scenario Additional Information During the initiation stage ...
Question 92: Project Scenario - Health and Safety Training Project: ABC C...
Question 93: HOTSPOT Scenario A photographer from Portraits Ltd, a profes...
Question 94: Scenario Additional Information Product Description (Exhibit...
Question 95: Scenario Additional Information (Exhibit) Further informatio...
Question 96: Scenario A photographer from Portraits Ltd, a professional p...
Question 97: MANAGING PRODUCT DELIVERY The team manager for the productio...
Question 98: Which 2 statements should be recorded under the Major risks ...
Question 99: Which principle is central to the quality theme and provides...
1 commentQuestion 100: Which of the following risk responses can be used for either...
Question 101: Project Scenario - Health and Safety Training Project: ABC C...
Question 102: Which project controls should be established for the Outsour...
Question 103: Scenario Additional Information Chief Executive Officer (CEO...
Question 104: Additional Information Product Description (Exhibit) Quality...
Question 105: Which role is responsible for providing the customer's quali...
Question 106: One of the senior managers of the company that is developing...
Question 107: Scenario Additional Information Product Description (Exhibit...
Question 108: HOTSPOT Column 1 is a list of entries from the Daily Log tha...
Question 109: Without a Risk Register how can project risks, the progress ...
Question 110: Scenario Additional Information Product Description (Exhibit...
Question 111: If Project tolerances were threatened, who needs to be notif...
Question 112: Which 2 statements should be recorded under the Reasons head...
Question 113: The project is now in stage 2. The Project Manager has heard...
Question 114: Scenario: Techniques, processes and procedures 1. Any threat...
Question 115: This question provides a number of changes which may or may ...
Question 116: Project Scenario - Health and Safety Training Project: ABC C...
Question 117: Scenario Product Summary A list of customers will be collate...
Question 118: During stage 1 the level of performance expected from the se...
Question 119: Using the Project Scenario and the Extract from Stage Plan f...
Question 120: Product Summary A list of customers will be collated. This w...
Question 121: Using the Project Scenario and the Extract from Stage Plan f...
Question 122: Whilst identifying the mailing costs for the calendars the P...
Question 123: Project Scenario Calendar Project (Note: The companies and p...
Question 124: Two weeks after starting work the Team Manager noticed that ...
Question 125: Which of the following management products ARE updated as pa...
Question 126: The executive identified that there would be a benefit to th...
Question 127: During which of the following activities is the Project Prod...
Question 128: Starting Up a project is triggered by which of the following...
Question 129: Which of the following statements best describes what a risk...
Question 130: Scenario Additional Information During the initiation stage ...
Question 131: Which product should show that if anybody has any remaining ...
Question 132: Scenario: The Ministry of Food Hygiene (MFH) has a quality m...
Question 133: The senior user is concerned that the trainers' limited avai...
Question 134: Which is a correctly defined acceptance criterion for the tr...
Question 135: The delivery of the pilot courses has been split into two se...
Question 136: Additional Information Product Description (Exhibit) Quality...
Question 137: Additional Information Extract from the Communication Manage...
Question 138: Scenario Additional Information During the initiation stage ...
Question 139: Additional Information Extract from the Communication Manage...
Question 140: Scenario A photographer from Portraits Ltd, a professional p...
Question 141: Which 2 statements explain why the CEO should be appointed a...
Question 142: Which of the following statements is False regarding the Ris...
Question 143: Scenario A photographer from Portraits Ltd, a professional p...
Question 144: The project is part of a program to develop more training co...
Question 145: Which 2 alternative actions apply to the proposed Executive ...
Question 146: Which of the following is False? A Successful project manage...
Question 147: The executive identified that there would be a benefit to th...
Question 148: Scenario Additional Information Product Description (Exhibit...
Question 149: Which of the following principles describes this statement?"...
Question 150: Who is responsible for confirming stage and project progress...
Question 151: M1ich statement is an appropriate entry for the outline Busi...
Question 152: Towards the end of stage 2, the stage 3 plan is being prepar...
Question 153: The project is approaching the end of stage 3, and stage 4 i...
Question 154: Additional Information Product Description (Exhibit) Quality...
Question 155: Who is responsible for committing user resources to the proj...
Question 156: The team member collating the list of customers has now fore...
Question 157: No Benefits Review Plan has been developed. Where should the...
Question 158: Scenario Additional Information During the initiation stage ...
Question 159: Who is responsible for committing user resources to the proj...
Question 160: Scenario A central government department, the Ministry of Fo...
Question 161: Which project controls should be established for the Outsour...
Question 162: Additional Information A photographer from Portraits Ltd, a ...
Question 163: When considering the business options in the business case, ...
Question 164: Scenario Additional Information Product Description (Exhibit...
Question 165: The project is at the start of stage 3, and there will be si...
Question 166: Which of the following statements would NOT be included in t...
Question 167: Which 2 statements explain why the Sales Manager should be a...
Question 168: A construction company that is one of ABC Company's key clie...
Question 169: Which of the following is NOT an objective of Initiating a P...
Question 170: Based on lessons from previous projects that used the ABC Co...
Question 171: This question provides a number of changes which may or may ...
Question 172: Which of the following statements is TRUE with regard to exp...
Question 173: Scenario Product Summary A list of customers will be collate...
Question 174: Which 2 statements explain why Central Records should be app...
Question 175: Project Scenario - Health and Safety Training Project: ABC C...
Question 176: Scenario: Techniques, processes and procedures 1. Any threat...
Question 177: If Project tolerances were threatened, who needs to be notif...
Question 178: Which of the following statements is true of the business in...
Question 179: The project is now in stage 2. The Project Manager has heard...
Question 180: Scenario A photographer from Portraits Ltd, a professional p...
Question 181: Who is responsible for ensuring that Communication Managemen...
Question 182: During stage 2, if the Project Manager decides to recommend ...
Question 183: Scenario Additional Information Chief Executive Officer (CEO...
Question 184: It is now late October and the project is in stage 3. The la...
Question 185: During stage 2, if the Project Manager decides to recommend ...
Question 186: Which statement is an appropriate entry for the outline Busi...
Question 187: Scenario Additional Information Chief Executive Officer (CEO...
Question 188: Which statement applies to the Introduction section?...
Question 189: Which 2 alternative actions apply to the proposed user assur...
Question 190: The Team Manager has received notification that the new hard...
Question 191: Scenario Product Summary A list of customers will be collate...
Question 192: Scenario Additional Information Product Description (Exhibit...
Question 193: At the end of stage 2, an external consultant responsible fo...
Question 194: Scenario A photographer from Portraits Ltd, a professional p...
Question 195: Project Scenario - Health and Safety Training Project: ABC C...
Question 196: Which statement is an appropriate entry for the project appr...
Question 197: There is no Project Brief. How can there be a common underst...
Question 198: Scenario Additional Information Extract from the Communicati...
Question 199: It is now late October and the project is in stage 3. The la...
Question 200: The delivery of the pilot courses has been split into two se...
Question 201: Scenario Additional Information Chief Executive Officer (CEO...
Question 202: During previous projects, stakeholders became confused when ...
Question 203: Project Scenario Calendar Project (Note: The companies and p...
Question 204: Project Scenario - Health and Safety Training Project: ABC C...
Question 205: Scenario Additional Information Extract from the Communicati...
Question 206: Additional Information Chief Executive Officer (CEO): He sta...
Question 207: Which product should show that the project has been closed p...
Question 208: The Health and Safety Training Project is closing as planned...
Question 209: HOTSPOT Scenario A photographer from Portraits Ltd, a profes...
Question 210: Project Scenario - Health and Safety Training Project: ABC C...
Question 211: HOTSPOT Scenario: Techniques, processes and procedures 1. An...
Question 212: Additional Information Extract from the Communication Manage...
Question 213: Scenario Additional Information During the initiation stage ...
Question 214: Project Scenario - Health and Safety Training Project: ABC C...
Question 215: The government agency held a seminar for training organizati...
Question 216: Extract from the Project Product Description (with errors) (...
Question 217: At the end of stage 2, an external consultant responsible fo...
Question 218: Which 2 statements should be recorded under the Expected ben...
Question 219: Scenario: The Ministry of Food Hygiene (MFH) has a quality m...
Question 220: Project Scenario - Health and Safety Training Project: ABC C...
Question 221: The project is using PRINCE2's recommended risk management p...
Question 222: Scenario Additional Information Chief Executive Officer (CEO...
Question 223: MANAGING PRODUCT DELIVERY The team manager for the productio...
Question 224: Use the 'Additional Information' in the Scenario Booklet to ...
Question 225: Which statement is an appropriate entry for the Lessons Log?...
Question 226: During which of the following activities is the Project Prod...
Question 227: This question provides a number of changes which may or may ...
Question 228: Project Scenario Calendar Project (Note: The companies and p...
Question 229: The project is now in stage 2. The Project Manager has heard...
Question 230: Who would be responsible for maintaining the Configuration I...
Question 231: Scenario Additional Information Extract from the Communicati...
Question 232: Scenario Additional Information During the initiation stage ...
Question 233: Which management product defines the detailed nature, purpos...
Question 234: Additional Information Extract from the Communication Manage...
Question 235: Project Scenario - Health and Safety Training Project: ABC C...
Question 236: It is now late October and the project is in stage 3. The la...
Question 237: Column 1 is a list of entries from the Daily Log that occurr...
Question 238: The project is approaching the end of stage 4 and all work w...
Question 239: MANAGING A STAGE BOUNDARY The project is approaching the end...
Question 240: HOTSPOT Project Scenario Calendar Project (Note: The compani...
Question 241: The project is using PRINCE2's recommended risk management p...
Question 242: Scenario A central government department, the Ministry of Fo...
Question 243: Although it is not specified in the current corporate brandi...
Question 244: This question provides a number of changes which may or may ...
Question 245: Which statement is an appropriate entry for the project appr...
Question 246: Product Summary A list of customers will be collated. This w...
Question 247: Scenario A central government department, the Ministry of Fo...
Question 248: The executive has set the following tolerances for stage 2: ...
Question 249: Which statement applies to the Introduction section?...
Question 250: Scenario Additional Information (Exhibit) Further informatio...
Question 251: While deciding on how the work of the project should be appr...
Question 252: Who is responsible for the initial creation of the Configura...
Question 253: The Health and Safety Training Project is closing as planned...
Question 254: A quality review of the 'marketing materials' has started. T...
Question 255: The project is in stage 2. The project manager is reviewing ...
Question 256: An external consultant has signed a contract and agreed a wo...
Question 257: STARTING UP A PROJECT Here are three actions carried out by ...
Question 258: A change authority has been appointed for the project. Durin...
Question 259: Which statement is TRUE with regard to technical stages?...
Question 260: Additional Information Extract from the Communication Manage...
Question 261: Which statement is TRUE with regard to technical stages?...
Question 262: HOTSPOT Scenario A photographer from Portraits Ltd, a profes...
Question 263: The 'classroom-based training materials' will be used as the...
Question 264: This question provides a number of changes which may or may ...
Question 265: None of the reviewers have proof-reading skills....
Question 266: Who is responsible for ensuring that the value-for-money sol...
Question 267: Project Scenario - Health and Safety Training Project: ABC C...
Question 268: During stage 3, project costs are increasing but there will ...
Question 269: Which product should show that the project has been closed p...
Question 270: Scenario Additional Information (Exhibit) Further informatio...
Question 271: HOTSPOT Product Summary A list of customers will be collated...