Your company changed its executives due to the lack of benefits realization and previous corruption issues. The new management has informed you that as of now, this will not change any process in the portfolio and everything will remain the same. However, only the risk tolerance for the organization will be impacted, what will you do as a portfolio manager?
Correct Answer: B
Explanation Multiple options look appealing, however the organization risk tolerance is part of the strategic plan and the new management has informed the portfolio manager that no changes are needed. The portfolio manager will only update the risk tolerance in the strategic plan and continue work accordingly. This type of questions is situational and you should pay attention to specific words such as "risk tolerance of the organization"