Portfolio Prioritization Model is included in the Portfolio management plan and guides the ongoing decisions as to which portfolio components should be added, terminated, or changed; which of the following is correct regarding the Prioritization Model purpose and content?
Correct Answer: C
Explanation The Prioritization Model guides the ongoing decisions as to which portfolio components should be added, terminated, or changed, as well as prioritizes and balances the component mix over time; it Contains criteria to ensure alignment to strategic goals, expected return on investment (ROI), investment risks, and dependencies. Scoring elements may be based on strategic alignment, financial benefits, financial costs, risk, and dependencies to determine an overall scoring and ranking.