Throughout the course of the portfolio lifecycle, components are initiated, terminated and updated. In order to be initiated, portfolio components receive go/no-go decisions during governance meetings. During which process the go/no-go decisions are taken?
Correct Answer: C
Explanation The purpose of the Authorize Portfolio process is to activate selected portfolio components by allocating resources to develop component proposals or execute portfolio components; update relevant portfolio reports such as funding updates, resource assignments, and allocations; and document governance decisions