One of the key stakeholders came to you asking you to add more metrics because she thinks that it would give the portfolio management a better view of the actual progress. For her the more metrics you have the better. What should your opinion be regarding this?
Correct Answer: C
Explanation It does not matter how many metrics you have as long as you have it all covered. The scenario here does not require escalation. The portfolio management office should be prepared to develop new metrics when appropriate and delete or change metrics that are no longer relevant to the stakeholders or that no longer support the organizational strategy and objectives. The quantity of metrics should not overwhelm the stakeholders to ensure the metrics are actively tracked and understood.