A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs. What should the project manager do?
Correct Answer: B
The project manager should set up a meeting with key stakeholders to clarify requirements. Clear communication is essential in project management, especially when working with remote teams or teams in different countries. By engaging key stakeholders, including the development team and the client, the project manager can address any differences in interpretation and ensure that everyone is on the same page regarding the client's needs. This proactive approach can help prevent rework and delays in the project schedule. References: 1.How to manage Client Expectations in Project Management: A Comprehensive Guide 2.Chapter 4: Understanding and Meeting Client Expectations - Project Management 3.Client Management: How to Win and Retain Clients - ProjectManager