Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time. What should the project manager do?
Correct Answer: B
As a project manager you don't just make one-way decisions. It should always be a collaborative decision. Option A is forcing. Option B is providing options for a team meeting to go over the options and hear out other team members. Also, not able to fulfil the acceptance criteria is an issue for successfully completing the project. PM needs to document the issue and have a discussion with the team.