A project for Company A was successfully delivered within scope, schedule, and budget by the end of the last iteration. However, during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value. What should the project manager have done to avoid this perception?
Correct Answer: B
Defining product backlog priorities with the sponsor and key stakeholders to deliver business benefits is an important step to ensure that the project is aligned with the business's needs and objectives, and that it delivers the expected value.