A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach. Why did the project manager choose a hybrid approach?
Correct Answer: C
Without knowing what is the requirement, as a project manager you cannot plan or schedule. Scope of a project comes from requirements. Schedule development can only be done scope is defined and validated - because it is Hybrid.