一家公司推出了最新的零售管理系統,並將專案移交給營運團隊。營運團隊發現,該系統未能滿足許多日常需求,且專案支援時間有限。專案團隊已解散,合約資源也不再負責該專案。因此,營運團隊面臨眾多客戶問題。
專案負責人最初應該做什麼來避免這種情況?
Correct Answer: D
The project lead should have involved the operations stakeholders during the planning phase of the project.
This would have ensured that the system was designed to meet the day-to-day requirements of the operations team. Additionally, it would have allowed for the identification of necessary support hours and resources. By involving operations stakeholders early in the project, the project lead could have avoided the issues that arose after the project was handed over to operations. References: Project Management Professional (PMP) Examination Content Outline, June 2015, PMI; A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition, Project Management Institute, Inc., 2017.